Project status

August – October 2024


  • Type 4 and 5 Villas: The facades are almost complete, and the interiors have been prepared for the finishing stage. Additionally, the windows and frames have been fully installed.
  • Type 2 Villas and part of Type 3 Villas: Work on sanitary installations and facades is underway, marking consistent progress in preparing the exteriors and interiors of these villas.
  • Type 1 Villas: In some units, plastering work has begun, and the installation of interior frames is in progress.
  • Pontoon: The pontoon construction is nearing completion, adding extra value and functionality to the complex, especially for recreational and relaxation activities by the water.

July 2024


  • Facade in progress for type 4 and 5 villas
  • Installation of polystyrene on terraces for type 2 villas
  • Completion of technological gaps and installation of sewer pipes for all villas
  • Completion of electrical installations and grounding

May – June 2024


  • Installation of thermal insulation on the facade for type 4 and 5 villas
  • Completion of masonry work for type 2 villas
  • Thermal installation work (underfloor heating) for type 5 villas
  • Exterior joinery for type 4 and 5 villas
  • Completion of sanitary installation work for type 4 and 5 villas
  • Completion of rough-in electrical wiring work for type 2, 4, and 5 villas

April 2024


  • Plastering works for type 5 villas
  • Terrace waterproofing for type 4 villas
  • Masonry works for type 2 villas
  • Ground floor casting for type 1 villas
  • Electrical and sanitary installation works for type 4 & 5 villas

March 2024


  • Completed structures for type 4 and 5 villas
  • Electrical and sanitary installation works have started for type 4 and 5 villas
  • Concrete columns over the 2nd floor for type 2 villas
  • Concrete beam foundation for type 1 villas

February 2024


  • Masonry for type 4 and 5 villas
  • Foundation beams and ground floor for type 2 villas
  • Baseboards for grounding of type 1, 2, and 3 villas
  • Sewer pipes for type 3 villas

January 2024


  • Special foundations with piles for Type 1 villas
  • Floor slabs for Type 4 and 5 villas
  • Electrical installations works for Type 2 villas
  • Technological gaps through foundations for plumbing and electrical installations (Type 2, 4 and 5 villas )
  • Installation works for domestic and rainwater sewer pipelines for Type 2 villas

November 2023


  • Promenade / pontoon area setup
  • Installation works for domestic and rainwater sewer pipelines for Type 4 and 5 villas
  • Pillar casting for Type 4 and 5 villas
  • Electrical installations works for Type 4 and 5 villas
  • Foundations for Type 2 villas

October 2023


  • Systematization of the terrain
  • Support walls for the consolidation of the terrain
  • Ground infrastructure works (roads, sewerage, installations)
  • Foundations for the first 9 houses

December 2022


  • The Marina Snagov project is born

August – October 2024


  • Type 4 and 5 Villas: The facades are almost complete, and the interiors have been prepared for the finishing stage. Additionally, the windows and frames have been fully installed.
  • Type 2 Villas and part of Type 3 Villas: Work on sanitary installations and facades is underway, marking consistent progress in preparing the exteriors and interiors of these villas.
  • Type 1 Villas: In some units, plastering work has begun, and the installation of interior frames is in progress.
  • Pontoon: The pontoon construction is nearing completion, adding extra value and functionality to the complex, especially for recreational and relaxation activities by the water.

July 2024


  • Facade in progress for type 4 and 5 villas
  • Installation of polystyrene on terraces for type 2 villas
  • Completion of technological gaps and installation of sewer pipes for all villas
  • Completion of electrical installations and grounding

May – June 2024


  • Installation of thermal insulation on the facade for type 4 and 5 villas
  • Completion of masonry work for type 2 villas
  • Thermal installation work (underfloor heating) for type 5 villas
  • Exterior joinery for type 4 and 5 villas
  • Completion of sanitary installation work for type 4 and 5 villas
  • Completion of rough-in electrical wiring work for type 2, 4, and 5 villas

April 2024


  • Plastering works for type 5 villas
  • Terrace waterproofing for type 4 villas
  • Masonry works for type 2 villas
  • Ground floor casting for type 1 villas
  • Electrical and sanitary installation works for type 4 & 5 villas

March 2024


  • Completed structures for type 4 and 5 villas
  • Electrical and sanitary installation works have started for type 4 and 5 villas
  • Concrete columns over the 2nd floor for type 2 villas
  • Concrete beam foundation for type 1 villas

February 2024


  • Masonry for type 4 and 5 villas
  • Foundation beams and ground floor for type 2 villas
  • Baseboards for grounding of type 1, 2, and 3 villas
  • Sewer pipes for type 3 villas

January 2024


  • Special foundations with piles for Type 1 villas
  • Floor slabs for Type 4 and 5 villas
  • Electrical installations works for Type 2 villas
  • Technological gaps through foundations for plumbing and electrical installations (Type 2, 4 and 5 villas )
  • Installation works for domestic and rainwater sewer pipelines for Type 2 villas

November 2023


  • Promenade / pontoon area setup
  • Installation works for domestic and rainwater sewer pipelines for Type 4 and 5 villas
  • Pillar casting for Type 4 and 5 villas
  • Electrical installations works for Type 4 and 5 villas
  • Foundations for Type 2 villas

October 2023


  • Systematization of the terrain
  • Support walls for the consolidation of the terrain
  • Ground infrastructure works (roads, sewerage, installations)
  • Foundations for the first 9 houses

December 2022


  • The Marina Snagov project is born
  • Send your contact details so you can download the project presentation with plans and prices.

    [email-download download_id=”119135″ contact_form_id=”119159″]

    • Send your contact details so you can download the project presentation with plans and prices.

      [email-download download_id=”119135″ contact_form_id=”119159″]

      • Trimite datele de contact pentru a putea descărca prezentarea proiectului cu planuri și prețuri.

        [email-download download_id=”118898″ contact_form_id=”118897″]

        • Trimite datele de contact pentru a putea descărca prezentarea proiectului cu planuri și prețuri.

          [email-download download_id=”118898″ contact_form_id=”118897″]