Project status
July 2024
- Facade in progress for type 4 and 5 villas
- Installation of polystyrene on terraces for type 2 villas
- Completion of technological gaps and installation of sewer pipes for all villas
- Completion of electrical installations and grounding
May – June 2024
- Installation of thermal insulation on the facade for type 4 and 5 villas
- Completion of masonry work for type 2 villas
- Thermal installation work (underfloor heating) for type 5 villas
- Exterior joinery for type 4 and 5 villas
- Completion of sanitary installation work for type 4 and 5 villas
- Completion of rough-in electrical wiring work for type 2, 4, and 5 villas
April 2024
- Plastering works for type 5 villas
- Terrace waterproofing for type 4 villas
- Masonry works for type 2 villas
- Ground floor casting for type 1 villas
- Electrical and sanitary installation works for type 4 & 5 villas
March 2024
- Completed structures for type 4 and 5 villas
- Electrical and sanitary installation works have started for type 4 and 5 villas
- Concrete columns over the 2nd floor for type 2 villas
- Concrete beam foundation for type 1 villas
February 2024
- Masonry for type 4 and 5 villas
- Foundation beams and ground floor for type 2 villas
- Baseboards for grounding of type 1, 2, and 3 villas
- Sewer pipes for type 3 villas
January 2024
- Special foundations with piles for Type 1 villas
- Floor slabs for Type 4 and 5 villas
- Electrical installations works for Type 2 villas
- Technological gaps through foundations for plumbing and electrical installations (Type 2, 4 and 5 villas )
- Installation works for domestic and rainwater sewer pipelines for Type 2 villas
November 2023
- Promenade / pontoon area setup
- Installation works for domestic and rainwater sewer pipelines for Type 4 and 5 villas
- Pillar casting for Type 4 and 5 villas
- Electrical installations works for Type 4 and 5 villas
- Foundations for Type 2 villas
October 2023
- Systematization of the terrain
- Support walls for the consolidation of the terrain
- Ground infrastructure works (roads, sewerage, installations)
- Foundations for the first 9 houses
July 2024
- Facade in progress for type 4 and 5 villas
- Installation of polystyrene on terraces for type 2 villas
- Completion of technological gaps and installation of sewer pipes for all villas
- Completion of electrical installations and grounding
May – June 2024
- Installation of thermal insulation on the facade for type 4 and 5 villas
- Completion of masonry work for type 2 villas
- Thermal installation work (underfloor heating) for type 5 villas
- Exterior joinery for type 4 and 5 villas
- Completion of sanitary installation work for type 4 and 5 villas
- Completion of rough-in electrical wiring work for type 2, 4, and 5 villas
April 2024
- Plastering works for type 5 villas
- Terrace waterproofing for type 4 villas
- Masonry works for type 2 villas
- Ground floor casting for type 1 villas
- Electrical and sanitary installation works for type 4 & 5 villas
March 2024
- Completed structures for type 4 and 5 villas
- Electrical and sanitary installation works have started for type 4 and 5 villas
- Concrete columns over the 2nd floor for type 2 villas
- Concrete beam foundation for type 1 villas
February 2024
- Masonry for type 4 and 5 villas
- Foundation beams and ground floor for type 2 villas
- Baseboards for grounding of type 1, 2, and 3 villas
- Sewer pipes for type 3 villas
January 2024
- Special foundations with piles for Type 1 villas
- Floor slabs for Type 4 and 5 villas
- Electrical installations works for Type 2 villas
- Technological gaps through foundations for plumbing and electrical installations (Type 2, 4 and 5 villas )
- Installation works for domestic and rainwater sewer pipelines for Type 2 villas
November 2023
- Promenade / pontoon area setup
- Installation works for domestic and rainwater sewer pipelines for Type 4 and 5 villas
- Pillar casting for Type 4 and 5 villas
- Electrical installations works for Type 4 and 5 villas
- Foundations for Type 2 villas
October 2023
- Systematization of the terrain
- Support walls for the consolidation of the terrain
- Ground infrastructure works (roads, sewerage, installations)
- Foundations for the first 9 houses